Chấp Thuận Đầu Tư Dự Án Đường Dây 500kV Kết Nối LNG Bạc Liêu - Thốt Nốt

National Power Transmission Corporation Approved for 500kV LNG Bac Lieu - Thot Not Transmission Line Project

The National Power Transmission Corporation (EVNNET) has recently received approval for the 500kV LNG Bac Lieu - Thot Not power transmission line project, a critical initiative aimed at enhancing power transmission capabilities in Southern Vietnam. This significant development marks a crucial step in addressing the region's electricity demand while ensuring national energy security amid growing consumption needs.



The project is expected to resolve electricity shortages in the region while simultaneously ensuring national energy security in the context of increasing electricity demand. This approval represents an important milestone in Vietnam's national power grid development strategy.



Detailed Project Information

The 500kV LNG Bac Lieu - Thot Not transmission line project has a total length of approximately 63 km, traversing Bac Lieu province. The transmission line is designed with a capacity of 2,000 MVA, utilizing the most advanced power transmission technology available.



The project will be implemented with a total estimated investment of around 1,500 billion VND, utilizing state budget funds and other legal capital sources.



Implementation Timeline

According to the plan, the project will be implemented over 2 years, from 2023 to 2024. The project will be divided into three main phases:


  • Technical design and land acquisition
  • Construction
  • Acceptance and commissioning

Route Location

The 500kV LNG Bac Lieu - Thot Not transmission line starts at the LNG Bac Lieu substation and ends at the Thot Not substation. The route passes through the following areas:


  • Bac Lieu City
  • Phuoc Long District
  • Vinh Loi District
  • Hong Dan District
  • Thoi Binh District

Significance and Benefits of the Project

The 500kV LNG Bac Lieu - Thot Not transmission line project offers numerous practical benefits for Southern Vietnam and the country as a whole:


  • Enhanced Power Transmission Capacity: Addresses the overload situation in Southern Vietnam, particularly in Bac Lieu province and neighboring provinces.
  • Energy Security Assurance: Strengthens the national power grid connection, ensuring stable electricity supply for residents and production.
  • Economic and Social Development Support: Creates favorable conditions for industrial, agricultural, and service development in the region.
  • Renewable Energy Promotion: Facilitates the integration of solar power and wind power plants into the national power grid.

Challenges and Solutions

During the implementation of the project, EVNNET will face several challenges:


  • Land Acquisition: The project passes through numerous residential areas, requiring reasonable and transparent compensation policies.
  • Weather Conditions: Southern Vietnam frequently experiences storms and floods, necessitating appropriate construction planning.
  • Occupational Safety: Ensuring absolute safety for workers and the community during construction.

To address these challenges, EVNNET has developed detailed plans, mobilized the best resources, and applied modern construction technologies.



Conclusion

The approval of the 500kV LNG Bac Lieu - Thot Not transmission line project represents a significant advancement in Vietnam's national power grid development strategy. The project not only addresses the urgent electricity demand in Southern Vietnam but also contributes to the sustainable development of Vietnam's power industry.



The National Power Transmission Corporation is committed to implementing the project on schedule, ensuring quality and efficiency, thereby contributing to national energy security and supporting socio-economic development.



Project Technical Specifications Summary

Project Name500kV LNG Bac Lieu - Thot Not Transmission Line
InvestorNational Power Transmission Corporation (EVNNET)
Total Length63 km
Design Capacity2,000 MVA
Total Investment1,500 billion VND
Implementation Period2 years (2023-2024)
Implementation AreaBac Lieu Province